{"count":6,"requests":[{"requested_start":"2027-01-18","requested_end":"2027-03-01","org_code":"MSD-9","facility":{"code":"MSL-2","hazard_class":"ROUTINE","name":"Materials & Structures Lab Bay 2"},"state":"APPROVED","progress":[{"position":1,"status":"complete","code":"SAFETY","label":"Safety Review"},{"position":2,"status":"complete","code":"READINESS","label":"Facility Readiness Review"},{"position":3,"status":"complete","code":"SCHEDULE","label":"Scheduling Confirmation"}],"principal_investigator":"T. Nakagawa","current_gate":null,"title":"Fatigue coupon screening, additively manufactured Inconel 718","request_no":"TR-000006"},{"requested_start":"2027-02-01","requested_end":"2027-02-12","org_code":"MSD-3","facility":{"code":"DROP-132","hazard_class":"CRITICAL","name":"Microgravity Drop Tower (132 m)"},"state":"DRAFT","progress":[{"position":1,"status":"pending","code":"SAFETY","label":"Safety Review"},{"position":2,"status":"pending","code":"READINESS","label":"Facility Readiness Review"},{"position":3,"status":"pending","code":"SCHEDULE","label":"Scheduling Confirmation"}],"principal_investigator":"S. Vashisht","current_gate":null,"title":"Capillary flow in an irregular container geometry","request_no":"TR-000005"},{"requested_start":"2027-04-05","requested_end":"2027-06-18","org_code":"MSD-7","facility":{"code":"ECTC-3","hazard_class":"CRITICAL","name":"Engine Component Test Cell 3"},"state":"RETURNED","progress":[{"position":1,"status":"returned","code":"SAFETY","label":"Safety Review"},{"position":2,"status":"pending","code":"READINESS","label":"Facility Readiness Review"},{"position":3,"status":"pending","code":"SCHEDULE","label":"Scheduling Confirmation"}],"principal_investigator":"D. Marchetti","current_gate":null,"title":"Combustor liner thermal cycling to 2,000 cycles","request_no":"TR-000004"},{"requested_start":"2027-01-11","requested_end":"2027-01-29","org_code":"LTP-2","facility":{"code":"ICE-1","hazard_class":"ELEVATED","name":"Icing Research Tunnel"},"state":"IN_SAFETY","progress":[{"position":1,"status":"current","code":"SAFETY","label":"Safety Review"},{"position":2,"status":"pending","code":"READINESS","label":"Facility Readiness Review"},{"position":3,"status":"pending","code":"SCHEDULE","label":"Scheduling Confirmation"}],"principal_investigator":"H. Okonkwo","current_gate":"SAFETY","title":"Supercooled large droplet accretion on a swept wing section","request_no":"TR-000003"},{"requested_start":"2027-03-15","requested_end":"2027-05-30","org_code":"MSD-11","facility":{"code":"EPVF-1","hazard_class":"CRITICAL","name":"Electric Propulsion Vacuum Facility 1"},"state":"IN_SCHEDULE","progress":[{"position":1,"status":"complete","code":"SAFETY","label":"Safety Review"},{"position":2,"status":"complete","code":"READINESS","label":"Facility Readiness Review"},{"position":3,"status":"current","code":"SCHEDULE","label":"Scheduling Confirmation"}],"principal_investigator":"N. Beaumont","current_gate":"SCHEDULE","title":"12 kW Hall thruster erosion characterisation","request_no":"TR-000002"},{"requested_start":"2027-02-08","requested_end":"2027-02-26","org_code":"LTP-4","facility":{"code":"SWT-8X6","hazard_class":"ELEVATED","name":"Supersonic Wind Tunnel (8 x 6 ft)"},"state":"APPROVED","progress":[{"position":1,"status":"complete","code":"SAFETY","label":"Safety Review"},{"position":2,"status":"complete","code":"READINESS","label":"Facility Readiness Review"},{"position":3,"status":"complete","code":"SCHEDULE","label":"Scheduling Confirmation"}],"principal_investigator":"A. Rutherford","current_gate":null,"title":"Inlet distortion survey, 1/6-scale nacelle","request_no":"TR-000001"}],"gates":["SAFETY","READINESS","SCHEDULE"]}